Progress on Ward 3 Short-Term Family Housing Structure
Here is the latest weekly report on construction progress. The contractors are finished with the foundation system, and they have poured the first-floor slab. The podium slab in progress, which is a big milestone for the project. Underground work on mechanical, electrical, and plumbing is underway. Site grading is being done as weather permits. The PEPCO transformer is coming in April. Substantial completion is currently projected for the end of 2019/early 2020.
And here is the Draft Good Neighbor Protocol, outlining how the shelter will be run. It provides proposed agreements on: Maintenance of the Property, Safety and Security, Conduct and Behavior, Communications and Mutual Respect.